Question: Using the Incremental Milestones Method for activity status calculation, what is the status of the following activity; Contractor XYZ has an agreement for $ 1

Using the Incremental MilestonesMethod for activity status calculation, what is the status of the following activity;
Contractor XYZ has an agreement for $1,750,000 to install 80 caissons that have an average depth of 120 LF. To date, they have completed a portion of the work as detailed below. They are preparing their first estimate payment and would like to status the pay estimate and the schedule activity based on the progress that they have made to date, but they have only included a single schedule activity upon which to place this progress. How much money is XYZ due for this work on the current pay estimate?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!