Question: Using the information below, calculate reorder point and total cost for the company that utilizes EQO model. Annual demand = 20,000 Annual holding cost =
Using the information below, calculate reorder point and total cost for the company that utilizes EQO model.
Annual demand = 20,000
Annual holding cost = $10/unit
Ordering cost = $75
Lead time = 5 days
| 300 units & $3,000 | ||
| 400 units & $5,477 | ||
| 200 units & $2,000 | ||
| 350 units & $5, 277 | ||
| 400 units & $5,350 |