Question: Using the information displayed in the following table, identify the critical path. Activity Name Successor Duration A B, C, D 5 B E 2 C

Using the information displayed in the following table, identify the critical path.

Activity Name

Successor

Duration

A

B, C, D

5

B

E

2

C

E

10

D

E

7

E

None

2

a.

A-C-E

b.

A-D-E

c.

A-E-D

d.

A-B-E