Question: Using the information displayed in the following table, identify the critical path. A. A-B-E B. A-C-E C. A-D-E D. A-E-D Activity Name Successor Duration A
Using the information displayed in the following table, identify the critical path.
A. A-B-E B. A-C-E C. A-D-E D. A-E-D
Activity Name Successor Duration A B, C, D 5 B E 2 C E 10 D E 7 E None 2