Question: Using the information for the International Capital project provided below, calculate the variance (ote 2) for activity G. Hint: use formula 7.2 for ote, standard

Using the information for the International
Using the information for the International Capital project provided below, calculate the variance (ote 2) for activity G. Hint: use formula 7.2 for ote, standard deviation Time in Workdays Activity Optimistic Most Likely Pessimistic A 10 B 2 2 8 2 5 8 D 16 19 28 E 6 24 F 1 7 13 G 4 10 28 H 5 I $ 8 17 J 2 5 8 K 17 29 45 None of the values provided 13 18 16 14 12