Question: Using the information from a project below: Predecessor Duration (Days) 10 9 13 3.1 Construct the network diagram (AON) and identify the Critical Path. (10)

 Using the information from a project below: Predecessor Duration (Days) 10

Using the information from a project below: Predecessor Duration (Days) 10 9 13 3.1 Construct the network diagram (AON) and identify the Critical Path. (10) 3.2 Calculate the Early Start; Late Start; Early Finish 8" Late Finish for all activities. (10) 3.3 Compute the 'slack" time for each activity. (5}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!