Question: Using the information given, do the following: (i) Identify the critical path. (ii) Determine expected project duration. Activity Immediate Predecessor(s) Duration Start - - aStart5bStart5cStart4da6eb9fd,
Using the information given, do the following: (i) Identify the critical path. (ii) Determine expected project duration.
ActivityImmediate Predecessor(s)DurationStart--aStart5bStart5cStart4da6eb9fd, e2hc6gf, h3ih1Endi, gStep by Step Solution