Question: Using the information given, do the following: ( i ) Identify the critical path. ( ii ) Determine expected project duration. Activity Immediate Predecessor (
Using the information given, do the following:
i Identify the critical path.
ii Determine expected project duration.
Activity Immediate
Predecessors Duration
Start
a Start
b Start
c Start
d a
e b
f d e
h c
g f h
i h
End i g