Question: Using the information given, in the figures below, develop a precedence notation CPM network for the bridge project described. Certain logical relationships are implied by

Using the information given, in the figures below, develop a precedence notation CPM network for the bridge project described. Certain logical relationships are implied by the bar chart that has been supplied to you by the field superintendent who has been chosen to run the job. According to contract specifications, your company must submit a network scheduling (CPM) to the owner. Knowing that you are a CPM expert, your boss has given you the job of setting up the network. He or she also has asked you to calculate the project duration in working days. The duration of each activity can be developed from the dates given on the bar chart. 8.4 Using the information given in the figures below, develop a precedence notation CPM network for the bridge project described. Certain logical relationships are implied by the bar chart that has been supplied to you by the field superintendent who has been chosen to run the job. According to contract specifications your company must submit a network scheduling (CPM) to the owner. Knowing that you are
Bar chart schedule for bridge project
(based on an example in Clough and Sears, Construction Project Management).
8.4 Using the information given in the figures below, develop a
precedence notation CPM network for the bridge project
described. Certain logical relationships are implied by the
bar chart that has been supplied to you by the field superin-
tendent who has been chosen to run the job. According to
contract specifications your company must submit a net-
work scheduling (CPM) to the owner. Knowing that you are
a CPM expert, your boss has given you the job of setting up
the network. He or she also has asked you to calculate the
project duration in working days. The duration of each activ-
ity can be developed from the dates given on the bar chart.
Mobilization and procurement activities are as follows:
Hints
There is only one excavation crew.
There is one set of formwork material for footers and
abutments.
Project duration should be approximately 65 days long.
General sequence of activities:
Excavation, piles driven, footer, abutment, and deck
Forming, pouring, curing, and stripping
To calculate the workdays from the bar chart, assume
June 17 is a Thursday. Workdays are Monday through
Friday.
Example project, bridge profile.
Example project, bridge transverse section.
Bar chart schedule for bridge project
(based on an example in Clough and Sears, Construction Project Management).
Please help me in making a CPM Chart based on the given information.
Using the information given, in the figures

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!