Question: Using the information given in the figures below, develop a precedence notation CPM network for the bridge project described. Certain logical relationships are implied by

Using the information given in the figures below, develop a precedence notation CPM network for the bridge project described. Certain logical relationships are implied by the bar chart that has been supplied to you by the field superintendent who has been chosen to run the job. According to contract specifications your company must submit a network scheduling (CPM) to the owner. Knowing that you are a CPM expert, your boss has given you the job of setting up the network. He or she also has asked you to calculate the project duration in working days. The duration of each activity can be developed from the dates given on the bar chart.

Mobilization and procurement activities are as follows:

Act 1 2 23 4 5 1 6 6 Duration 10 5

• There is only one excavation crew.

• There is one set of formwork material for footers and abutments.

• Project duration should be approximately 65 days long.

• General sequence of activities:

• Excavation, piles driven, footer, abutment, and deck 

• Forming, pouring, curing, and stripping 

• To calculate the workdays from the bar chart, assume June 17 is a Thursday. Workdays are Monday through Friday.

Act 1 2 23 4 5 1 6 6 Duration 10 5 3 15 10 15 7 25 Description Shop drawings, abutment, and deck steel Shop drawings, foot steel Move in Deliver piles Shop drawings, girders Deliver abutment and deck steel Deliver footer steel Deliver girders Followers 11 6 7,8 9 26 16 12 28

Step by Step Solution

3.43 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Total project duration 65 working days Key CPM Seque... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!