Question: Using the information given in the table below, assuming that the project team will work for 5 days per w and that there is no

Using the information given in the table below, assuming that the project team will work for 5 days per w and that there is no delay in starting all tasks. (i) Find the critical path (9 marks) (ii) Duration of the critical path (8 marks) 110 (iii) Non-critical tasks and the float (free slack). ( 8 marks) WISHING YOU ALL THE BEST