Question: Using the information in Table 12-7, construct a PERT network just like the chart you see in the picture and answer each of the following
Using the information in Table 12-7, construct a PERT network just like the chart you see in the picture and answer each of the following questions:
a. What is the expected project completion data?
b. What is the scheduled start and completion date for each activity?
c. Which activities are on the critical path?
d. How long can noncritical path activities be delayed without jeopardizing the overall completion date for this project?

The pert chart must be made just like the one shown in the picture above!
It must contain the the items that are shown in the legend in the picture above.
Here is the data you will need to complete the Pert Chart:
Time estimate
Activity Predecessor (weeks)
A Secure state approval 4
B Identify 20-bed unit to A 1
be used
C Move existing residents B 1
D Clean space C 2
E Develop architectural plans A 9
F Install new heating and E 4
ventilation systems
G Install security systems E 2
H Move walls; renovate F 4
I Identify new equipment A 1
J Order new equipment I 1
K Unpack and inspect new J 1
equipment
L Install new equipment D,K,H 3
M Reassign staff A 1
N Identify new staffing needs M 1
O Advertise for new staff N 3
P Interview for new staff O 2
Q Select new hires P 3
R Develop care plan protocols M 1
S Train staff R,Q,M,L 1
T Modify quality assurance plans S 2
U Coordinate with hospital T 4
discharge planners
V Complete internal audit U,G 1
Answer all questions!
DO NOT MAKE IT LIKE ANY PREVIOUS PERT CHARTS IT MUST BE MADE JUST LIKE THE CHART IN THE PICTURE WITH THE INFORMATION INSIDE THE LEGEND WHICH IS ALSO IN THE PICTURE. I need the ES,ID,EF,SL,DESCRIPTION,LS,DURATION, AND LF.
Here is the data again.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
