Question: Using the information in the figures below, develop a precedence notation CPM network for the bridge project described. Certain logical relationships are implied by the

Using the information in the figures below, develop a precedence notation CPM network for the bridge project described. Certain logical relationships are implied by the bar chart that has been supplied to you by the field superintendent who has been chosen to run the job. According to contract specifications your company must submit a net- work scheduling (CPM) to the owner. Knowing that you are a CPM expert, your boss has given you the job of setting up the network. He or she also has asked you to calculate the project duration in working days. The duration of each activity can be developed from the dates given on the bar chart.
Mobilization and procurement activities are as follows:
\table[[Act,Duration,Description,Followers],[1,10,\table[[Shop drawings,],[abutment, and deck steel]],11],[2,5,Shop drawings, foot steel,6],[3,3,Move in,7,8],[4,15,Deliver piles,9],[5,10,Shop drawings, girders,26],[11,15,Deliver abutment and,16],[6,7,deck steel,12],[26,25,Deliver footer steel,28]]
Bar chart schedule for bridge project
(based on an example in Clough and Sears, Construction Project Management).
There is only one excavation crew.
There is one set of formwork material for footers and abutments.
Project duration should be approximately 65 days long.
General sequence of activities Excavation, piles driven, footer, abutment, and deck
Forming, pouring, curing, and stripping
To calculate the workdays from the bar chart, assume June 17 is a Thursday. Workdays are Monday through Friday.
Using the information in the figures below,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!