Question: Using the information in the figures below, develop a precedence notation CPM network for the bridge project described. Certain logical relationships are implied by the
Using the information in the figures below, develop a precedence notation CPM network for the bridge project described. Certain logical relationships are implied by the bar chart that has been supplied to you by the field superintendent who has been chosen to run the job. According to contract specifications your company must submit a net work scheduling CPM to the owner. Knowing that you are a CPM expert, your boss has given you the job of setting up the network. He or she also has asked you to calculate the project duration in working days. The duration of each activity can be developed from the dates given on the bar chart.
Mobilization and procurement activities are as follows:
tableActDuration,Description,FollowerstableShop drawings,abutment and deck steelShop drawings, foot steel,Move inDeliver piles,Shop drawings, girders,Deliver abutment and,deck steel,Deliver footer steel,
Bar chart schedule for bridge project
based on an example in Clough and Sears, Construction Project Management
There is only one excavation crew.
There is one set of formwork material for footers and abutments.
Project duration should be approximately days long.
General sequence of activities Excavation, piles driven, footer, abutment, and deck
Forming, pouring, curing, and stripping
To calculate the workdays from the bar chart, assume June is a Thursday. Workdays are Monday through Friday.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock