Question: Using the information in the table, Create a network diagram Find the critical path through the network diagram you created Find the critical time of
- Using the information in the table,
- Create a network diagram
- Find the critical path through the network diagram you created
- Find the critical time of the critical path of the network diagram you created
| Task | Predecessor(s) | Duration Estimate |
| A | None | 1 |
| B | None | 2 |
| C | None | 3 |
| D | A | 6 |
| E | A | 5 |
| F | B | 3 |
| G | B | 2 |
| H | B | 8 |
| I | C | 6 |
| J | D | 4 |
| K | D, E | 10 |
| L | E | 3 |
| M | F | 1 |
| N | F | 6 |
| O | G | 3 |
| P | M, N | 2 |
| Q | H | 8 |
| R | I | 1 |
| S | I | 1 |
| T | R, S | 4 |
| U | J, K | 1 |
| V | L | 2 |
| W | U, V | 6 |
| X | O, Q | 7 |
| Y | W, T | 3 |
| Z | W, Y | 22 |
Note 1: This problem requires only single-point estimates
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts