Question: Using the information in the table, determine a schedule for these five jobs using the critical ratio sequence. Job Process Time Due Date A 2
Using the information in the table, determine a schedule for these five jobs using the critical ratio sequence.
| Job | Process Time | Due Date |
| A | 2 | 7 |
| B | 8 | 16 |
| C | 4 | 4 |
| D | 10 | 17 |
| E | 5 | 15 |