Question: Using the information in this table, assuming that the project team will work a standard working week (5 working days in a week) and that

Using the information in this table, assuming that the project team will work a standard working week (5 working days in a week) and that all tasks will start as soon as possible, then: 1. Draw the network diagram. 2. Determine the critical path. 3. Calculate each path's slack (duration of the project in weeks including EF, LF, ES, LS, Slack). Duration Predecessor/s Description (Working days) 5 Requirement Analysis A 15 Systems Design B 25 Programming C 30 Telecoms D 10 Hardware Installation E, F 10 Integration G 5 System Testing H 5 Training/Support I 1 Handover and Go-Live J