Question: Using the information on the table below, what is the slack time for activity B . Activity Predecessors Estimated Duration A - 5 B A

Using the information on the table below, what is the slack time for activity B.
Activity Predecessors Estimated Duration
A -5
B A 5
C A 6
D B,C 13
E B 6
F D 4
G C 9
H E, F, G 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!