Question: Using the Longest Task Time (LTT) heuristic to assign tasks, what will be the correct order of tasks assigned to fill the workstations? Make sure

Using the Longest Task Time (LTT) heuristic to assign tasks, what will be the correct order of tasks assigned to fill the workstations? Make sure you indicate the order of tasks in the workstation, the total task time in the workstation, and the idle time in the workstation. Use Number of Following Tasks (NFT) as a tie breaker. Assume the desired production rate is 4 units per hour. Task times are in minutes.

Using the Longest Task Time (LTT) heuristic to

A B E G Task Task Time Predecessors A 4 B 2 A, C 6 5 E 2 B F 5 D G 10 E, F H 9 F, G I 2 H Total = 45 D F H I =