Question: Using the MPS record created in Question 1 and shown below, as well as the Bill of Materials (BOM) shown below, complete the two MRP
- Using the MPS record created in Question 1 and shown below, as well as the Bill of Materials (BOM) shown below, complete the two MRP records by filling in the yellow cells.
- If the answer is zero (0), enter a 0 in the cell.
- Remember, FOQ is Fixed Order Quantity and L4L is Lot for Lot.
- SHOW YOUR WORK! I need to see the MRP chart, and show how you got each number if you want partial credit. Otherwise, if a number is wrong it is wrong!
MPS Record and Bill of Materials (BOM):
Item: A
Lot Sizing Rule: FOQ = 100
Lead time: 1 week
Beginning Inventory: 80
Week
1
2
3
4
5
6
7
8
9
10
11
12
Gross Requirements
25
25
25
25
30
30
30
30
35
35
35
35
Projected On Hand (80)
55
30
5
80
50
20
90
60
25
90
55
20
Planned Orders (MPS)
0
0
100
0
0
100
0
0
100
0
0
0
Item: D
Lot Sizing Rule: FOQ = 144
Lead Time: 3 weeks
Parent: A
Beginning Inventory: 120
Week
1
2
3
4
5
6
7
8
9
10
11
12
Gross Requirements
Scheduled Receipts
0
0
0
0
0
0
0
0
0
0
0
0
Projected On Hand (120)
Planned Orders (MRP)
Planned Order Releases (MRP Release Date)
Complete These Two MRP Records:
Item: E
Lot Sizing Rule: L4L
Lead Time: 2 weeks
Parent: A
Beginning Inventory: 0
Week
1
2
3
4
5
6
7
8
9
10
11
12
Gross Requirements
Scheduled Receipts
0
0
0
0
0
0
0
0
0
0
0
0
Projected On Hand (120)
Planned Orders (MRP)
Planned Order Releases (MRP Release Date)
Step by Step Solution