Question: Using the Network Diagram below, describe the relationships between each activity pertaining to lags. Notes: Ensure you use proper terms such as Start and Finish
Using the Network Diagram below, describe the relationships between each activity pertaining to lags.
Notes:
- Ensure you use proper terms such as "Start" and "Finish"
- Assume the lags are referring to "days"
- Activities can have multiple relationships
| Activity | Lag Description |
| F | Cannot start until Activity A finishes Cannot finish until 2 days after Activity E finishes |
| E | |
| D | |
| C | |
| B | Cannot start until Activity A finishes |

0 A 5 5 F 19 Design 5 system 11 System documentation 0 0 5 10 16 3 19 12 E 17 Lag 2 Test Lag 2 4 system 16 2 17 3 B 4 C 10 10 D 16 Lag 3 Order Lag 4 O 0 Install Lag 1 0 0 Install hardware 0 hardware software 0 3 8 2 10 10 6 16 Legend ES ID EF SL Description SL LS Duration LF
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts