Question: Using the new PMBOK methodology for computing forward and backward passes, if a project has an Early Start of 1 and a Duration of 3

Using the "new" PMBOK methodology for computing forward and backward passes, if a project has an Early Start of 1 and a Duration of 3, what is the Early Finish?
Select one:
i.
4
ii.
None of the above
iii.
3
iv.
2