Question: using the PERT 3-point estimating method and you have a Pessimistic duration (P) of 20 days, an Optimistic duration (O) of 11 days, and a
using the PERT 3-point estimating method and you have a Pessimistic duration (P) of 20 days, an Optimistic duration (O) of 11 days, and a most likely duration (M) of 14 days, then what is the expected duration (E)?