Question: Using the PERT document Download PERT document and the provided information in Table 1, answer the following questions: Create a network diagram. Identify all possible

Using the PERT document Download PERT document and the provided information in Table 1, answer the following questions:

  1. Create a network diagram.
  2. Identify all possible paths.
  3. Identify the critical path.

Hint: there should be 12 possible paths

If you want to do Extra Credit worth 50 points: using the data below and MS Project Application, create a schedule. One of the videos within this exercise provides guidance, as well as, leveraging your learning from your IPM6010 Project Scheduling course. For clarity, if you complete items 1-3 w/o error you get 100 points; and if you also complete the extra credit w/o error, this assignment will be 150 points in total. Good luck!

ID

Description

Predecessor

Duration

A

Survey

None

5.7

B

Soils report

A

20,8

C

Traffic Design

A

30.2

D

Lot Layout

A

6.2

E

Approve Design

B,C,D

80.0

F

Illumination

E

14.3

G

Drainage

E

31.7

H

Landscape

E

25.3

I

Signing

E

20.8

J

Bid Proposal

F,G,H,I

10.5

You will lose one point for each mistake or incorrect item on your answers.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!