Question: Using the PERT technique, let's say you estimate an activity to most likely take 2 0 hours . the best case is 1 0 hours

Using the PERT technique, let's say you estimate an activity to most likely take 20 hours . the best case is 10 hours and the worst case is 30 hours . what is expected time?
19.3