Question: Using the priority list T 3 , T 7 , T 2 , T 5 , T 1 , T 6 , T 9 ,

Using the priority list T3, T7, T2, T5, T1, T6, T9, T4, T8, schedule the project below with two processors.
Task Time Required Tasks that must be completed first
T110
T24
T37
T48
T57 T1, T2, T3
T611 T3
T73 T4, T5
T82 T5
T95 T6
Task 6 is done by
Select an answer
starting at time
Task 8 is done by
Select an answer
starting at time
The finishing time for the schedule is