Question: Using the priority list T 3 , T 7 , T 1 , T 4 , T 2 , T 6 , T 8 ,

Using the priority list T3, T7, T1, T4, T2, T6, T8, T9, T5, schedule the project below with two processors. Using the priority list T3,T7,T1,T4,T2,T6,T8,T9,T5, schedule the project below with two processors.
List the task numbers of the tasks processor one works on, in order. For example, if they work on T1 then
T4 then T7, enter: 1,4,7. Ignore idle time.
T1(11)
T2(4)
T3(5)
T4(9)
T5(8)
T6(2)
T7(3)
T8(11)
T9(12)
List the task numbers of the tasks processor one works on, in order. For example, if they work on T1 then T4 then T7, enter: 1,4,7. Ignore idle time.