Question: Using the process time formula for the assembly work center in Dallas (ASSY1000), use the formula test function to calculate the total duration to build

Using the process time formula for the assembly
Using the process time formula for the assembly work center in Dallas (ASSY1000), use the formula test function to calculate the total duration to build 200 bicycles, with a setup of 30 minutes, 3 splits, and 15 minutes of labor for each base quantity of 15 bikes. 1030 minutes 130 minutes 80 minutes 96.7 minutes 430 minutes