Question: Using the same data as the previous problem, if the manager used a simple exponential smoothing method with an alpha value of 0.4, what would
Using the same data as the previous problem, if the manager used a simple exponential smoothing method with an alpha value of 0.4, what would be the forecast for January 28 if the forecast for January 21 is 95?
Group of answer choices
88
79.4
93
87
84.6