Question: Using the table below, calculate the expected time for the activity for activity A. Activity Optimistic Time Most Likely Time Pessimistic Time Expected Time Variance
Using the table below, calculate the expected time for the activity for activity A.
| Activity | Optimistic Time | Most Likely Time | Pessimistic Time | Expected Time | Variance |
| A | 1 | 3 | 8 | ? |
Group of answer choices
2.50
3
3.50
3.83
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts