Question: Using the table below, calculate the expected time for the activity for activity A. Activity Optimistic Time Most Likely Time Pessimistic Time Expected Time Variance

Using the table below, calculate the expected time for the activity for activity A.

Activity Optimistic Time Most Likely Time Pessimistic Time Expected Time Variance
A 1 3 8 ?

Group of answer choices

2.50

3

3.50

3.83