Question: Using the information given, calculate the expected time for each of the project activities. Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic

Using the information given, calculate the expected time for each of the project activities.

Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)
A 3 6 9 none
B 3 5 7 A
C 4 7 12 A
D 4 8 10 B
E 5 10 16 C
F 3 4 5 D,E
G 3 6 8 D,E
H 5 6 10 F
I 5 8 11 G
J 3 3 3 H,I

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!