Question: Using the table below, construct the project network and calculate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish times and the slack associated

Using the table below, construct the project network and calculate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish times and the slack associated with each activity. Which of the choices captures the earliest and latest start times of B and the slack of G correctly?

Activity

Immediate

Duration

Predecessors

A

-

6

B

A

8

E

B

4

G

-

20

Earliest Start Time of B = 6, Latest Start Time of B = 6, Slack of G = 0.

Earliest Start Time of B = 6, Latest Start Time of B = 8, Slack of G = 0.

Earliest Start Time of B = 8, Latest Start Time of B = 8, Slack of G = 4.

Earliest Start Time of B = 8, Latest Start Time of B = 8, Slack of G = 2.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!