Question: Using the table below, construct the project network and calculate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish times and the slack associated
Using the table below, construct the project network and calculate the Earliest Start, Earliest Finish, Latest Start, and Latest Finish times and the slack associated with each activity. Which of the choices captures the earliest and latest start times of B and the slack of G correctly?
| Activity | Immediate | Duration |
| Predecessors | ||
| A | - | 6 |
| B | A | 8 |
| E | B | 4 |
| G | - | 20 |
| Earliest Start Time of B = 6, Latest Start Time of B = 6, Slack of G = 0. | ||
| Earliest Start Time of B = 6, Latest Start Time of B = 8, Slack of G = 0. | ||
| Earliest Start Time of B = 8, Latest Start Time of B = 8, Slack of G = 4. | ||
| Earliest Start Time of B = 8, Latest Start Time of B = 8, Slack of G = 2. |