Question: . Using the table below draw a network diagram and calculate the critical path forward pass, backward pass, float. Activities Duration Start A B C

. Using the table below draw a network diagram

. Using the table below draw a network diagram and calculate the critical path forward pass, backward pass, float. Activities Duration Start A B C D E F G H Preceeding Activities Start Start A,B A C,D C E G 0 6 8 9 10 7 7 9 10