Question: Using the table below: Make a PERT diagram for the problem it describes Find a compatible ordering of the tasks. Determine the minimal project time

Using the table below: Make a PERT diagram for the problem it describes Find a compatible ordering of the tasks. Determine the minimal project time and the critical path: Task Time Preceding task A 10 None B 12 None C 15 None D 6 AC E 3 AB F 5 B.C G 7 D, F H D, E I 9 E, F