Question: Q: Below are the tables given, in which is telling the time needed for each of a number of tasks and which tasks must immediately
Q: Below are the tables given, in which is telling the time needed for each of a number of tasks and which tasks must immediately precede them. Make a PERT diagram for each problem and determine the project time and critical path. A)
| Task | Time | Preceding time |
| A | 10 | NONE |
| B | 12 | NONE |
| C | 15 | NONE |
| D | 6 | A, C |
| E | 3 | A, B |
| F | 5 | B, C |
| G | 7 | D, F |
| H | 6 | D, E |
| I | 9 | E, F |
B)
| Task | Time | Preceding time |
| A | 11 | NONE |
| B | 13 | NONE |
| C | 12 | NONE |
| D | 14 | NONE |
| E | 8 | A, C, D |
| F | 6 | A, B, D |
| G | 10 | A, B, C |
| H | 5 | B, C, D |
| I | 9 | E, F, H |
| J | 7 | F, G, H |