Question: Using the Table of Dependencies below, network diagram. HAND DRAW the diagram on a piece of paper (8x11 landscape) Use the correct node and arrow

Using the Table of Dependencies below, network diagram.

  1. HAND DRAW the diagram on a piece of paper (8x11 landscape)
  2. Use the correct node and arrow format (Week 5 PPT) (2 marks)
    1. Show the legend on the bottom right of the paper
    2. correct AON formatting
  3. Go left to right - do not turn corners. (1 mark) a quick draft using just ID Code and arrows to determine how much room you will need.
  4. Answer the following questions on the bottom of the paper (5 marks)
    1. How many days will it take to finish the project?
    2. Which activity is a burst activity?
    3. Which activity is a merge activity?
    4. Which activity/activities have slack and how much?
    5. What is the critical path? (use correct notation)

A garden with a stone path - Table of dependencies

Code Task Duration (days) Predecessors
A Sketch out the new garden and pathway 2 -
B Purchase materials (stone, soil, plants) 1 A
C Dig out the garden area 3 B
D Excavate the pathway 4 B
E Install pathway stones 5 D
F Fill garden with soil 2 C
G Plant new plants 1 F
H Water thoroughly 1 F,G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!