Question: Using the Table of Dependencies below, network diagram. HAND DRAW the diagram on a piece of paper (8x11 landscape) Use the correct node and arrow
Using the Table of Dependencies below, network diagram.
- HAND DRAW the diagram on a piece of paper (8x11 landscape)
- Use the correct node and arrow format (Week 5 PPT) (2 marks)
- Show the legend on the bottom right of the paper
- correct AON formatting
- Go left to right - do not turn corners. (1 mark) a quick draft using just ID Code and arrows to determine how much room you will need.
- Answer the following questions on the bottom of the paper (5 marks)
- How many days will it take to finish the project?
- Which activity is a burst activity?
- Which activity is a merge activity?
- Which activity/activities have slack and how much?
- What is the critical path? (use correct notation)
A garden with a stone path - Table of dependencies
| Code | Task | Duration (days) | Predecessors |
| A | Sketch out the new garden and pathway | 2 | - |
| B | Purchase materials (stone, soil, plants) | 1 | A |
| C | Dig out the garden area | 3 | B |
| D | Excavate the pathway | 4 | B |
| E | Install pathway stones | 5 | D |
| F | Fill garden with soil | 2 | C |
| G | Plant new plants | 1 | F |
| H | Water thoroughly | 1 | F,G |