Question: Using the table provided answer the questions. ACTIVITY PREDECESSOR A TIME (Days) 10 B 23 C - 16 D A 14 E B 15 F
ACTIVITY PREDECESSOR A TIME (Days) 10 B 23 C - 16 D A 14 E B 15 F C,E 13 G D 15 H F 9 G,H 4 4.1. Draw the Activity-on-Node diagram for the above information. Calculate the duration of all possible paths on the network diagram. 4.2 4.3 Identify the critical path and state its duration.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
