Question: Using the table shown below: ID Activity Predecess Distributio a m b Variance= ors n (b-a)2/36 A Define Beta 2 4 6 Requirements B Design

Using the table shown below: ID Activity Predecess Distributio a m b Variance= ors n (b-a)2/36 A Define Beta 2 4 6 Requirements B Design A Beta 4 6 Application C Draft User A Beta 4 5 6 Manual D Prepare A Beta 6 8 10 Code E Test Code B,C Beta 2 3 4 F Correct Code E, D Beta 3 4 5 What is the chance of NOT finishing the project in 17 weeks? O 50% O 68% O 63% O 59%