Question: Using Information provided below: Te=(a+4m+b)/6 ID Activity Predecessors Distribution a (weeks) m (weeks) b (weeks) Variance= (b-a)2/36 A Define Beta 2 4 6 Requirements B


Using Information provided below: Te=(a+4m+b)/6 ID Activity Predecessors Distribution a (weeks) m (weeks) b (weeks) Variance= (b-a)2/36 A Define Beta 2 4 6 Requirements B Design A Beta 4 6 8 Application C Draft User A Beta 4 5 6 Manual D Prepare A Beta 6 8 10 Code E Test Code B,C Beta 2 3 4 F Correct Code E,D Beta 3 4 5 What is the chain of critical activities? O ACEF O ACDF O ABEF O ADEF