Question: Using the task duration probability data (in weeks), and precedence data shown below, answer the questions: a. Draw the network and identify the critical path

Using the task duration probability data (in weeks), and precedence data shown below, answer the questions:

a. Draw the network and identify the critical path for the project?

b.What are the expected duration and standard deviation of the project of the critical path?

Activity Low 10 5 4 15 ABCDEFGHIIKIN L M DOGT 17 10 

Activity Low 10 5 4 15 ABCDEFGHIIKIN L M DOGT 17 10 12 5 7 16 5 10 1919 11 10 Most High Likely 22 2792N 25 30 22112112 21 20 10 087166 18 27 11 16 26 268 42 16 18 41 45 38 31 18 1886200 31 38 16 32 38 Preceded. by None ABCCDELUHELH .F I.K. G 1. J Mean S l'is $ CP

Step by Step Solution

3.39 Rating (149 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer To answer the questions we need to first calculate the expected duration and va... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!