Using the task duration probability data (in weeks), and precedence data shown below, answer the questions: a.
Fantastic news! We've Found the answer you've been seeking!
Question:
Using the task duration probability data (in weeks), and precedence data shown below, answer the questions:
a. Draw the network and identify the critical path for the project?
b.What are the expected duration and standard deviation of the project of the critical path?
Related Book For
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray
Posted Date: