Question: You are creating a customer database for Winston-Salem Warthogs minor league baseball team. Draw a project network given the information below. Complete the forward and
How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncriticalactivities.
.png)
Time ID Description Predecessor (days) Systems design Subsystem A design Subsystem B design Subsystem C design Program A Program B Program C Subsystem A test Subsystem B test Subsystem C test Integration Integration test None 10 H,I,J
Step by Step Solution
3.38 Rating (160 Votes )
There are 3 Steps involved in it
The project is expected to take 16 days The project is not very ... View full answer