Question: Using the tasks below, create a precedence diagram, and then determine the duration needed to complete the tasks. Task Estimated Duration Dependencies A Confirm #
Using the tasks below, create a precedence diagram, and then determine the duration needed to complete the tasks.
Task Estimated Duration Dependencies
A Confirm # of Attendees 5 Min Start
B Print Name Tags 30 Min A
C Set Up Tables 30 Min A
D Confirm Catering 10 Min A
E Place Table Linens 20 Min C
F Place Name Tags 10 Min B, E
Which path is the Critical Path?
a) ADEF
b) ACEF
c) ABEF
d) ABF