Question: Using the tasks below, create a precedence diagram, determine the duration needed to complete the tasks, and label the critical path. Task Estimated Duration Dependencies
Using the tasks below, create a precedence diagram, determine the duration needed to complete the tasks, and label the critical path.
Task Estimated Duration Dependencies A Confirm # of Attendees 5 Min Start B Print Name Tags 30 Min A C Set Up Tables 30 Min A D Confirm Catering 10 Min A E Place Table Linens 20 Min C F Place Name Tags 10 Min B, E