Question: Using the template from our lecture, Critical Path Analysis for the following project. Your result should show: A graphic representation of the Critical Path Analysis.
Using the template from our lecture, Critical Path Analysis for the following project.
Your result should show:
- A graphic representation of the Critical Path Analysis.
- Highlight the critical path using different color of arrows.
Looking at the critical path diagram, answer the following two questions.
- Which activities are on the critical path?
- What is the length of the whole project?
| Activity | Immediate Predecessor | Time (Days) |
| A | - | 5 |
| B | A | 2 |
| C | A | 4 |
| D | B | 5 |
| E | B | 5 |
| F | C | 5 |
| G | E, F | 2 |
| H | D | 3 |
| I | G,H | 5 |