Question: Using the template from our lecture, do a Critical Path Analysis for the following project. Your result should show: 1. A graphic representation of
Using the template from our lecture, do a Critical Path Analysis for the following project. Your result should show: 1. A graphic representation of the Critical Path Analysis. 2. Highlight the critical path using thick or different color of arrows. Looking at the critical path diagram, answer the following two questions. 1. Which activities are on the critical path? 2. What is the length of the whole project? Activity A B C D E F G H Immediate Predecessor A A B B C D E,F Time (Days) 3 4 6 6 4 4 6 8