Question: Using the top - down method of forecasting project time and costs is the preferred method for situations involving strategic decision - making, projects with

Using the top-down method of forecasting project time and costs is the preferred method for situations involving strategic decision-making, projects with a high degree of uncertainty, and projects with an unstable scope.
True
False