Question: Using the Transportation Matrix , solve the transportation problem below using the Northwest Corner and Intuitive Lowest-Cost methods. Use the Northwest Corner method result
Using the "Transportation Matrix", solve the transportation problem below using the Northwest Corner and Intuitive Lowest-Cost methods. Use the Northwest Corner method result as the starting point and solve for the optimal solution using the Stepping-Stone method.
Show all steps and all calculations when doing the Stepping-Stone method. Solve for
- Northwest Corner method
- Intuitive Lowest-Cost method
- Stepping-Stone method
Plants Supply Destination Demand
Kansas City 35 Chicago 30
Omaha 50 St. Louis 65
Des Moines 50 Cincinnati 40
Total 135 tons Total 135 tons
| Transport cost from Plants to Destinations ($/ton) | |||
| Plants | Chicago | St. Louis | Cincinnati |
| Kansas City Omaha Des Moines | $4 6 8 | 3 7 2 | 3 6 5 |