Question: using this activity create the excel RACI chart Activity Description 100 Dig earth 200 Pour Foundation 300 Steel erection 400 Install roof 500 Install Glass

using this activity create the excel RACI chart
using this activity create the excel RACI chart
Activity Description 100 Dig earth 200 Pour Foundation 300 Steel erection 400 Install roof 500 Install Glass curtainwall 600 Protection on site 700 Drywall Duration Predecessor Resource 10 days None Excavation 20 Days 100 Concrete 30 days 200 Ironworks 15 days 300 Roofer 30 days 300 Glass 15 Days 400, 500 Carpenters 30 days 500 Carpenters

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!