Question: Using time - study techniques, an observer studies the placement of a 2 - foot by 8 - foot wall forms for a straight wall.
Using timestudy techniques, an observer studies the placement of a foot byfoot wall forms for a straight wall. Three carpenters are employed, and the observer breaks down the overall work process into the following operations:
Operation : Carpenters walk to get form. Operation : Carpenters pick up form. Operation : Carpenters take form to placement location. Operation : Carpenters position and put form in place. The following times in seconds are collected for each of cycles.
Assuming a rating factor of and an allowance factor of solve each of the following problems:
a Calculate a standard time in seconds per cycle.
b Calculate the standard time productivity in terms of carpenterhour per square foot of contact area.
c Assume that the estimator thinks that Operation can be reduced by onehalf the allotted time, and recalculate the standard time for the process.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock