Question: UsingJohnson's rule for2-machine scheduling, the sequenceis: Scheduled Order Job 1 E A D B C F 2 F E D B C A 3 B
UsingJohnson's rule for2-machine scheduling, the sequenceis:
| Scheduled Order | Job |
| 1 | E A D B C F |
| 2 | F E D B C A |
| 3 | B F A D C E |
| 4 | C D A E B F |
| 5 | C E A D F B |
| 6 | E A F C D B |
For the schedule developed usingJohnson's rule, the total length of time taken to complete the six jobs(including the 2ndoperation) =
enter your response here
hours (enter your response as a wholenumber).
Six jobs are to be processed through atwo-step operation. The first operation involvessanding, and the second involves painting. Processing times are asfollows:
| Job | Operation 1(hours) | Operation 2(hours) | ||
| A | 4 | 8 | ||
| B | 10 | 5 | ||
| C | 3 | 11 | ||
| D | 14 | 14 | ||
| E | 6 | 1 | ||
| F | 7 | 12 |