Question: UsingJohnson's rule for2-machine scheduling, the sequenceis: Scheduled Order Job 1 E A D B C F 2 F E D B C A 3 B

UsingJohnson's rule for2-machine scheduling, the sequenceis:

Scheduled Order Job
1

E

A

D

B

C

F

2

F

E

D

B

C

A

3

B

F

A

D

C

E

4

C

D

A

E

B

F

5

C

E

A

D

F

B

6

E

A

F

C

D

B

For the schedule developed usingJohnson's rule, the total length of time taken to complete the six jobs(including the 2ndoperation) =

enter your response here

hours (enter your response as a wholenumber).

Six jobs are to be processed through atwo-step operation. The first operation involvessanding, and the second involves painting. Processing times are asfollows:

Job Operation 1(hours) Operation 2(hours)
A 4 8
B 10 5
C 3 11
D 14 14
E 6 1
F 7 12

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!