Question: a - b ) Using Johnson's rule for 2 - machine scheduling, the sequence is: Job;Printing ( hours ) ;Binding ( hours ) T; 1

a-b) Using Johnson's rule for2-machine scheduling, the sequence is: Job;Printing (hours);Binding (hours)
T;10;8
U;3;4
V;6;2
W;12;7
X;5;1
Y;14;13
Z;9;11
Scheduled Order
Job
1
U
Part 2
2
Z
Part 3
3
Y
Part 4
4
T
Part 5
5
W
Part 6
6
V
Part 7
7
X
Part 8
c) For the schedule developed using Johnson's rule, the total length of time taken to complete the seven printing and binding jobs(including binding)= enter your response here hours (enter your response as a whole number). D) the idle time in binding shop based on the sequence developed using Johnson's rule : amount of hours?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!